Skip to main content
SES - NSW State Emergency Service NSW Government - Office of Environment and Heritage

NSW Flood Data Portal

Floodplain Risk Management Study and Plan

Lake Wyangan Floodplain Risk Management Study and Plan

EXECUTIVE SUMMARY

The Lake Wyangan Flood Study was completed by BMT WBM in March 2012. The outcome of this study was the production of flood inundation and flood risk mapping for the Lake Wyangan locality, generated from detailed hydrologic and hydraulic modelling of the catchment. The flood study represents the initial stage in the floodplain management process and establishes the basis for the current floodplain risk management study.

The objectives of the Lake Wyangan Floodplain Risk Management Study and Plan (FRMS&P) are to:

  • Identify and assess measures for the mitigation of existing flood risk;
  • Identify and assess planning and development controls to reduce future flood risks; and
  • Present a recommended floodplain management plan that outlines the best possible measures to reduce flood damages in the Lake Wyangan locality.

Additional Information

Field Value
Title Lake Wyangan Floodplain Risk Management Study and Plan
River Basin 410 - Murrumbidgee
Commission Date 1 March 2012
Publication Date 1 August 2013
Themes Land and Resource Management
Spatial Extent
© OpenStreetMap contributors
Council/LGA Griffith City Council
Author/ Prepared by BMT WBM Pty Ltd. Author: Darren Lyons
Publish date 1 February 2018
Update date 28 March 2018
Place Name Lake Wyangan
Approval State Approved
Submitted for approval 7 March 2018
Submitted by Durgananda Chaudhary
Approved 29 March 2018
Approved by dstazic
Identifier d68b6d61-7710-4cd5-9531-46445c8626ec