The Balranald Shire Council has engaged SKM to investigate flood protection for the towns of Balranald and Euston. This report presents the key outcomes of the work undertaken to date for the Balranald levee system, which have been used as the basis for the concept design.

A number of local and regional issues have been examined throughout this project. The key issues (and actions taken) are:

  • Aesthetic considerations required along river frontage between Ballendalla Street and Moa Street. Outcome: Examination of bank batters, height, landscaping and aesthetics required.
  • Landowner concerns over the construction of a levee in Mr Zaffina's property (RD 4,753 - 5,241), Outcome: Alignment pegged behind house - levee height required (approx. 2-3 metres).
  • Requirement for vehicle access along the levee. Outcome: Vehicle access to be provided unless the levee is situated adjacent to the road.
  • Protection of the caravan park. Outcome: Not required.
  • Appropriate freeboard allowance. Outcome: Review required.

Additional Information

Field Value
Title Balranald and Euston Flood Protection Works
River Basin 410 - Murrumbidgee
Publication Date 29 October 2002
Themes Land and Resource Management
Spatial Extent
© OpenStreetMap contributors
Council/LGA Balranald Shire Council
Author/ Prepared by Sinclair Knight Merz
Publish date 30 May 2019
Update date 26 June 2019
Approval State Approved
Submitted for approval 30 May 2019
Submitted by Akhil Sud
Approved 27 June 2019
Approved by jhudson