118 Flood Projects found

River Basin: 410 - Murrumbidgee

Filter Results
  • Flood Project
    Floodplain Risk Management Plan

    Narrandera Floodplain Risk Management Plan

    Completed
    Publication date: 27/03/2009
    There is a long history of flooding from the Murrumbidgee River in Narrandera. Serious flooding has been reported since settlement began over 150 years ago. Formal gauging of...

  • Flood Project
    Floodplain Risk Management Study and Plan

    Conargo - Floodplain Management Study & Plan - Flood Data Assessment Study...

    Completed
    Publication date: 01/12/2008
    Conargo Council intends to prepare a Floodplain Risk Management Study and Plan for the village of Conargo. The overall objectives of the Floodplain Risk Management Study will be...

  • Flood Project
    Flood study

    Murrumbidgee River Floodplain: Hay to Maude - Phase A Flood Study and Data Collection

    Completed
    Publication date: 01/01/2008
    The specific area of the Murrumbidgee River considered by this study is the reach between 11km upstream of Hay and just downstream of Maude. The Study area covers a total...

  • Flood Project
    Visual Levee Audits

    Hay Levee - Visual Audit of Urban Levees Non Tidal Areas of NSW

    Completed
    Publication date: 01/03/2007
    Hay is located in southwestern NSW, approximately 720 km south west of Sydney. The town is located on the Murrumbidgee River and is protected from flooding by a levee system...

  • Flood Project
    Visual Levee Audits

    Moulamein Levee - Visual Audit of Urban Levees Non Tidal Areas of NSW

    Completed
    Publication date: 01/02/2007
    Moulamein is located in southwestern NSW, approximately 660 km south west of Sydney. The town is located on the Edward River and is protected from flooding by a levee system...

  • Flood Project
    Visual Levee Audits

    Barham Levee - Visual Audit of Urban Levees Non Tidal Areas of NSW

    Completed
    Publication date: 01/02/2007
    Barham is located in southwestern NSW, approximately 805 km south west of Sydney. The town is located on the Murray River and is protected from flooding by a levee system...

  • Flood Project
    Visual Levee Audits

    Darlington Point Levee - Visual Audit of Urban Levees Non Tidal Areas of NSW

    Completed
    Publication date: 01/01/2007
    The Dams and Civil Unit of the Department of Commerce has been engaged by the Department of Natural Resources to carry out a visual audit for a number of individual flood levees...

  • Flood Project
    Flood study

    Griffith Flood Study

    Completed
    Publication date: 28/08/2006
    The Main Drain ‘J’ catchment covers an area of nearly 1,000 square kilometres, forming a moderately sized sub-catchment of the Murrumbidgee River Valley. The catchment extends...

  • Flood Project
    Floodplain Risk Management Plan

    Billabong Creek Floodplain Management Plan

    Completed
    Publication date: 01/05/2006
    The Billabong Creek FMP applies to the Billabong Creek floodplain situated between the Murray and Murrumbidgee Rivers in southern New South Wales. The floodplain extends from...

  • Flood Project
    Flood study

    Moulamein Levee Upgrade Flood Study

    Completed
    Publication date: 16/04/2006
    Moulamein is located in south-western New South Wales about 100 kilometres west of Deniliquin. The town is situated at the confluence of the Edward River and Billabong Creek...

  • Flood Project
    Visual Levee Audits

    Jindalee Creek Levee, Cootamundra

    Completed
    Publication date: 01/06/2005
    Cootamundra Shire Council commissioned Cardno Willing (NSW) Pty Ltd to investigate and design levee banks at Jindalee Creek, Cootamundra. The design was undertaken in two...

  • Flood Project
    Detailed Design

    Dudauman Creek Levee - Stockinbingal Final Design Report

    Completed
    Publication date: 01/06/2005
    Cootamundra Shire Council (CSC) commissioned Cardno Willing (NSW) Pty Ltd (CW) to investigate and design levee banks at Dudauman Creek, Stockinbingal. The design is to be...

  • Flood Project
    Floodplain Risk Management Study

    Billabong Creek Floodplain Management Study (Phase B Report)

    Completed
    Publication date: 01/06/2004
    Billabong Creek is situated between the Murray and Murrumbidgee Rivers in southern New South Wales. The study area, shown on Figure 1, covers that portion of the Billabong Creek...

  • Flood Project
    Visual Levee Audits

    Balranald and Euston Flood Protection Works

    Completed
    Publication date: 29/10/2002
    The Balranald Shire Council has engaged SKM to investigate flood protection for the towns of Balranald and Euston. This report presents the key outcomes of the work undertaken...

  • Flood Project
    Floodplain Risk Management Study

    Cootamundra Floodplain Management Study

    Completed
    Publication date: 01/06/2001
    The study area lies within the overall catchment of Muttama Creek. The township of Cootamundra is located in the upper reaches of Muttama Creek. Gundagai township is located on...

  • Flood Project
    Floodplain Risk Management Plan

    Cootamundra Floodplain Management Plan

    Completed
    Publication date: 01/06/2001
    The study area lies within the overall catchment of Muttama Creek. It includes the floodplain between Nash's Lane and the Cootamundra Lake site, being the West Jindalee Road....

  • Flood Project
    Guidance, Tools and Resources

    Murrumbidgee Province - Aboriginal Cultural Heritage Study

    Completed
    Publication date: 01/06/2001
    The Murrumbidgee Province of the Riverine Plain is three million hectares in extent, covering an area the size of Belgium. It is greater in size than the total area of protected...

  • Flood Project
    Flood study

    Narrandera Flood Study - Volume 1 Final Report

    Completed
    Publication date: 06/12/2000
    Narrandera is located on the Murrumbidgee River approximately 460 km west of the headwaters. Narrandera itself is a rural shire of approximately 4,177 square kilometres. The...

  • Flood Project
    Guidance, Tools and Resources

    Cooma Flood Mitigation Works Final Report On Phase 1 and 2 Investigations

    Completed
    Publication date: 01/03/2000
    In 1993-1994 the Snowy Mountains Engineering Corporation (SMEC) in association with the National Capital Planning Authority (NCPA) were engaged by the Cooma-Monaro Shire Council...

  • Flood Project
    Flood study

    Bungendore Flood Study

    Completed
    Publication date: 22/04/1999
    At present a large part of the commercial district of Bungendore is affected by flooding in the 1 in 100 year flood. In severe storms Turallo Creek and its tributaries can...